124
3
© 2007 Schneider Electric. All Rights Reserved.63230-216-229-B1
Commissioning
Checking Input Connections
Single-Phase Generator &
Voltages Delivered by 3 VT
Block Diagram
DE50708
* Detection of Plugged Connector (required for proper operation. Installed manually)
Procedure
1 Connect the single-phase voltage and current generator to the corresponding
test terminal boxes, using the plugs provided, according to the block diagram
above.
2 Turn the generator on.
3 Apply the generator V-N voltage set to the rated secondary phase-to-neutral
voltage of the VTs (that is, V
Ln
s = V
LLs
/3) between Sepam’s phase a voltage
input terminals (via the test box).
4 Inject the generator I current, set to the rated secondary current of the CTs
(namely, 1A or 5A) and in phase with the V-N voltage applied
(specifically,generator phase displacement α(V
Ln
, I) = 0°) to Sepam’s phase a
current input (via the text box).
5 Use the SFT2841 software to check the following:
b the value indicated for Ia phase current is approximately equal to the rated
primary current of the CT
b the value indicated for Va phase-to-neutral voltage is approximately equal to
the rated primary phase-to-neutral voltage of the VT (V
Ln
p = V
LL
p
/ 3)
b the value indicated for the phase displacement ϕa(Van, Ia) between the Ia
current and Van voltage is approximately equal to 0°
6 Proceed in the same way by circular permutation with the phase b and c voltages
and currents, to check the Ib, Vbn, ϕb(Vbn, Ib) and Ic, Vcn, ϕc(Vcn, Ic) values
7 Turn the generator off.
Kommentare zu diesen Handbüchern