Commissioning
Checking Sepam™ B80
Additional Voltage
Input Connections
Block Diagram
DE51259
* Detection of Plugged Connector (required for proper operation. Installed manually)
Procedure
Use the diagram above to perform the following steps
1 Turn the generator on.
2 Apply a voltage VN set to the rated secondary voltage of the additional VT
(V’
Ln
s = V’
LLs
/ 3).
3 Use the SFT2841 software to check that the measured voltage indicated V’an or
V’ab is approximately equal to the VT's rated primary phase-to-neutral voltage
(V’
Ln
p = V’
LLp
/ 3).
4 Turn the generator off when testing is complete.